Key Takeaway
Almost any sink, toilet, shower or tub can be moved in a remodel. How big the job is depends mainly on the drain, not the water lines: the distance to the existing drain and vent, the slope the new drain needs, and whether the floor is a wood subfloor over a crawl space or a concrete slab. Oregon requires a plumbing permit when a remodel relocates existing plumbing, with a rough-in inspection before the walls close. SKS Plumbing plans and plumbs remodels and home additions across Hillsboro and Washington County, open seven days a week. Call (503) 319-9348.
Almost any sink, toilet, shower or tub can be moved in a kitchen or bathroom remodel. What decides how big the job is, is the drain: how far the new fixture is from the existing drain and vent, the slope the new drain line needs, and whether the floor underneath is wood over a crawl space or a concrete slab. Water supply lines are the easy part and can go almost anywhere.
This guide covers what makes a plumbing move simple or involved, what the permit and inspections look like in Oregon, how the work fits into a remodel schedule, and what drives the cost, for homes in Hillsboro, Beaverton, Tigard and across Washington County.
What Makes Moving Plumbing Simple or Complicated
The drain decides the difficulty
Supply lines carry water under pressure, so they can run up, down and around. Drains work by gravity. Every drain needs a steady downhill slope back to the main drain line, and every fixture needs a vent so the drain flows freely and the trap holds its water seal. When you move a fixture, the question is always how to get a sloped drain and a vent from the new spot to the existing system.
That is why some moves that look small on a floor plan turn out to be large jobs, and some that look large are simple.
Crawl space or slab
Many Hillsboro and Beaverton homes from the 1970s through 1990s sit over a crawl space. Drains run under the floor joists, so a plumber can reroute them from below with little disruption to the room. Homes built on a concrete slab are different: moving a toilet or shower drain means cutting a trench in the concrete, laying the new pipe at the correct slope, and patching the floor. It is very doable, but it adds time and cost.
Distance from the existing stack
A fixture moved a few feet along the same wall can usually tie into the existing drain and vent. A fixture moved to the other side of the room, or to a new room, may need a new drain run and its own vent, sometimes all the way to the roof.

Common Moves and What Each Involves
Moving a toilet. A toilet needs a 3-inch drain and a vent. Moving it a short distance over a crawl space is often a few hours of work below the floor. Moving it across a room on a slab is a bigger job.
Moving a bathroom sink or vanity. One of the easier moves. The drain is small and a sink can often vent through the wall behind it.
Turning a tub into a walk-in shower. The drain usually moves to a new position under the shower pan, and the shower valve is often replaced at the same time. Our shower valve guide covers when that makes sense.
Moving a kitchen sink to an island. One of the bigger kitchen moves. With no wall behind the sink, the vent has to be handled another way, and the drain has to run under the floor to the island. Over a crawl space it is very doable.
Adding a bathroom or laundry room. New fixtures where there were none need new supply, drain and vent lines from the nearest connection point. In a basement, the drain may sit below the main sewer line, which can call for a pump.
Moving a washer. A washer needs hot and cold supply, a drain standpipe with a trap and vent, and ideally a pan or leak protection. Our washing machine hoses guide covers the leak side.
Permits and Inspections in Oregon
Moving plumbing needs a permit in Oregon. The state's Building Codes Division residential permits page lists a "remodel or addition that requires existing plumbing to be relocated" among the plumbing work that requires a permit, along with work that would "alter piping inside a wall, ceiling or under a floor." By contrast, it lists repairing or replacing "a sink, toilet, faucet not concealed in a wall" as work that does not.
The code behind those inspections is the Oregon Plumbing Specialty Code, which the Building Codes Division says "applies to the installation, alteration, repair, relocation, and replacement of plumbing systems." Drain sizing, slope and venting are all set by it, which is why a relocated fixture has to be planned, not improvised.
In practice, the plumbing contractor usually pulls the plumbing permit. The rough-in is inspected before the walls and floors are closed, and the final inspection happens once fixtures are installed. Our guide to plumbing permits and minor labels explains how that works in more detail. Whether your address falls under the City of Hillsboro or Washington County, the inspection steps are the same.

How Plumbing Fits Into the Remodel Schedule
Remodel plumbing happens in phases that follow the construction:
- 1Planning. Before demolition, we look at the plans, find the existing drain and vent lines, and confirm the new layout will work. This is when to find out that a move needs a slab cut or a new vent, not after the cabinets are ordered.
- 2Rough-in. After demolition and framing, before drywall. New supply, drain and vent lines go into the walls and floor, the lines are capped and pressure tested, and the work is inspected.
- 3Trim-out. After drywall, tile and finishes. Fixtures, faucets, valves and final connections go in, and everything is tested.
From our own jobs, a bathroom that keeps its fixtures in place usually needs about a day of rough-in work, while a bathroom with relocated fixtures takes one to two days of rough-in plus a day of trim-out. A full kitchen with an island sink move takes one to two days of rough-in. If you have a general contractor, we schedule around their timeline so plumbing does not hold up the job.
What Affects the Cost of Moving Plumbing
We do not quote prices without seeing the space and the plans, because the range is wide. These are the things that move it:
- Floor type. Wood subfloor over a crawl space costs less to work under than a concrete slab.
- Distance to the existing drain and vent. Short moves on the same wall cost less than a fixture moved across the room.
- Venting. A new vent run, especially through the roof, adds work. Island sinks need a specific venting approach.
- Number of fixtures. Moving one sink is a small job; moving a toilet, shower and vanity is a bigger one.
- What is found when the walls open. Galvanized supply pipe, old valves or a cracked drain are best replaced while everything is exposed. Our repiping signs guide explains what to look for.
Every SKS estimate is free and given in writing before work starts, broken down by phase so you can plan the budget.

Plan Your Remodel Plumbing
SKS Plumbing plans and plumbs kitchen and bathroom remodels, laundry moves, ADUs and home additions as part of our plumbing for remodels and home additions service, in Hillsboro, Beaverton, Tigard, Portland and the rest of Washington County. For fixture work without a layout change, see our bathroom plumbing and kitchen plumbing services. We are licensed and insured, Oregon CCB #243571.
We are open seven days a week. Call (503) 319-9348, or book a visit to talk through your plans and get a free estimate.
Frequently Asked Questions
Usually, yes. A toilet needs a 3-inch drain at the right slope and a vent, so the work depends on how far the new spot is from the existing drain and what is under the floor. Over a crawl space it is often straightforward; on a concrete slab the floor has to be cut and patched.
Yes. Oregon's Building Codes Division lists a remodel or addition that requires existing plumbing to be relocated as work that needs a plumbing permit. Replacing a sink, toilet or faucet in the same place generally does not. A licensed plumbing contractor can pull the permit for you.
It is one of the bigger kitchen moves, because an island sink needs a drain run under the floor and a venting method that works without a wall behind it. Over a crawl space it is very doable; on a slab it means cutting a trench in the concrete.
Twice, at minimum. The rough-in happens after demolition and framing, before drywall, and is inspected before the walls close. The trim-out happens after tile and finishes, when the fixtures are set and connected.
If the supply lines are galvanized or the valves are old, yes. Replacing them while the walls are already open costs far less than opening them again later.